Pacific VP30 Hinged Door Set -/30/30sm Installation

 

This tool is designed to filter the available results as you search. Once you have applied a filter, you may need to reset the filter to be able to see all other available options.

 

Please note:  Hardware is not included with our doors. However, we are pleased to help in sourcing high-quality hardware from ASSA ABLOY at an additional cost.

For BPIR Documents related to ASSA ABLOY hardware, please see: ASSA ABLOY 

For hardware from other suppliers, please refer to the individual hardware supplier for information.

 

To see our installation videos please click here.

Installation wall framing requirements

Pacific VP30 Hinged Door Set -/30/30sm

WALL TYPE: Korok / Speedwall
FRAME TYPE: Timber

Frame materials available:

  • Hardwood timber - Min density 580kg/m≥ (minimum thickness is 30mm)

Fasteners:

  • Frame - Screwed (10g self tapping) at 600mm centres nominal. Two screws per location. 
  • Stops - nailed (50 x 3.2mm) at 200mm centres.
  • Architrave - nailed (50 x 3.2mm) at 400mm centres.

Head Fixing (minimum):

  • Single door - none required

Wall type:

  • Korok panels with 13 mm FRR plasterboard on furring channels to one side. Trim opening to be framed with nom. 45 mm timber.

Wedging gap:

  • 0-10mm
F-D-VP30_VP60-T-KT1 image
WALL TYPE: Korok / Speedwall
FRAME TYPE: Timber

Frame materials available:

  • Hardwood timber - Min density 580kg/m≥ (minimum thickness is 30mm)

Fasteners:

  • Frame - Screwed (10g self tapping) at 600mm centres nominal. Two screws per location. 
  • Stops - nailed (50 x 3.2mm) at 200mm centres.
  • Architrave - nailed (50 x 3.2mm) at 400mm centres.

Head Fixing (minimum):

  • Single door - none required

Wall type:

  • Korok panels with 13 mm FRR plasterboard on furring channels to one side. Trim opening to be framed with nom. 45 mm timber.

Wedging gap:

  • 0-10mm
F-D-VP30_VP60-T-KT2 image
WALL TYPE: Korok / Speedwall
FRAME TYPE: Steel, 1-part

Frame materials available:

  • EGZ - 1.6mm
  • Cold rolled galvanized - 1.6mm

Fasteners:

  • Jamb fixing at 60mm centres minimum
  • 10 Gauge self tapping screws

Head Fixing (minimum):

  • Single door - 2 required
  • Paired door - 4 required

Wedging gap:

  • 0 - 15mm

Fire rating for unlined Speedpanel / Korok walls:

  • 51 mm wall: Max. FRR -/60/30
  • 64 mm wall: Max. FRR -/90/30
  • 78 mm wall: Max. FRR -/120/30

Integrity rating can be increased by 30 minutes by lining the wall one or both sides, up to a max. of 120 minutes.

Frame has to be filled with plasterboard, ceramic fibre blanket or grout to achieve 30 minute insulation rating.

Please note that when using this installation method the frame has to be built into the wall. It can't be installed in a pre-formed opening.

F-D-VP30_VP120-S-Speed image
WALL TYPE: Korok / Speedwall
FRAME TYPE: Steel, 1-part

Frame materials available:

  • EGZ - 1.6mm
  • Cold rolled galvanized - 1.6mm

Fasteners:

  • Jamb fixing 6 sets (i.e. 12 per jamb)
  • 10 x 75mm Gauge self tapping screws

Head Fixing (minimum):

  • Single door - none required
  • Paired door - 1 set

Wedging gap:

  • 0 - 15mm

Fire rating for unlined Speedpanel / Korok walls:

  • 51 mm wall: Max. FRR -/60/30
  • 64 mm wall: Max. FRR -/90/30
  • 78 mm wall: Max. FRR -/120/30

Integrity rating can be increased by 30 minutes by lining the wall one or both sides, up to a max. of 120 minutes.

Frame has to be filled with plasterboard, ceramic fibre blanket or grout to achieve 30 minute insulation rating.

F-D-VP30_VP120-S-Speed_2 image
WALL TYPE: Korok / Speedwall
FRAME TYPE: Steel, 1-part

Frame materials available:

  • EGZ - 1.6mm
  • Cold rolled galvanized - 1.6mm

Fasteners:

  • Jamb fixing 6 sets (i.e. 12 per jamb)
  • 10g x 75mm self tapping screws

Head Fixing (minimum):

  • Single door - none required
  • Paired door - 1 set

Wedging gap:

  • 0 - 15mm

Fire rating for unlined Speedpanel / Korok walls:

  • 51 mm wall: Max. FRR -/60/30
  • 64 mm wall: Max. FRR -/90/30
  • 78 mm wall: Max. FRR -/120/30

Integrity rating can be increased by 30 minutes by lining the wall one or both sides, up to a max. of 120 minutes.

Frame has to be filled with plasterboard, ceramic fibre blanket or grout to achieve 30 minute insulation rating.

F-D-VP30_VP120-S-K1 image
WALL TYPE: Korok / Speedwall
FRAME TYPE: Steel, 1-part

Frame materials available:

  • EGZ - 1.6mm
  • Cold rolled galvanized - 1.6mm

Fasteners:

  • Jamb fixing 6 sets (i.e. 12 per jamb)
  • 10g x 75mm self tapping screws

Head Fixing (minimum):

  • Single door - none required
  • Paired door - 1 set

Wedging gap:

  • 0 - 15mm

Fire rating for unlined Speedpanel / Korok walls:

  • 51 mm wall: Max. FRR -/60/30
  • 64 mm wall: Max. FRR -/90/30
  • 78 mm wall: Max. FRR -/120/30

Integrity rating can be increased by 30 minutes by lining the wall one or both sides, up to a max. of 120 minutes.

Frame has to be filled with plasterboard, ceramic fibre blanket or grout to achieve 30 minute insulation rating.

F-D-VP30_VP120-S-K2 image
WALL TYPE: Korok / Speedwall
FRAME TYPE: Steel, 1-part

Frame materials available:

  • EGZ - 1.6mm
  • Cold rolled galvanized - 1.6mm

Fasteners:

  • Jamb fixing 6 sets (i.e. 12 per jamb)
  • 10g x 75mm self tapping screws

Head Fixing (minimum):

  • Single door - none required
  • Paired door - 1 set

Wedging gap:

  • 0 - 15mm

Fire rating for unlined Speedpanel / Korok walls:

  • 51 mm wall: Max. FRR -/60/30
  • 64 mm wall: Max. FRR -/90/30
  • 78 mm wall: Max. FRR -/120/30

Integrity rating can be increased by 30 minutes by lining the wall one or both sides, up to a max. of 120 minutes.

Frame has to be filled with plasterboard, ceramic fibre blanket or grout to achieve 30 minute insulation rating.

F-D-VP30_VP120-S-K3 image
WALL TYPE: Korok / Speedwall
FRAME TYPE: Steel, 1-part

Frame materials available:

  • EGZ - 1.6mm
  • Cold rolled galvanized - 1.6mm

Fasteners:

  • Jamb fixing 6 sets (i.e. 12 per jamb)
  • 10g x 75mm self tapping screws

Head Fixing (minimum):

  • Single door - none required
  • Paired door - 1 set

Wedging gap:

  • 0 - 15mm

Fire rating for unlined Speedpanel / Korok walls:

  • 51 mm wall: Max. FRR -/60/30
  • 64 mm wall: Max. FRR -/90/30
  • 78 mm wall: Max. FRR -/120/30

Integrity rating can be increased by 30 minutes by lining the wall one or both sides, up to a max. of 120 minutes.

Frame has to be filled with plasterboard, ceramic fibre blanket or grout to achieve 30 minute insulation rating.

F-D-VP30_VP120-S-K4 image
WALL TYPE: Korok / Speedwall
FRAME TYPE: Steel, 1-part

Frame materials available:

  • EGZ - 1.6mm
  • Cold rolled galvanized - 1.6mm

Fasteners:

  • Jamb fixing 6 sets (i.e. 12 per jamb)
  • 10g x 75mm self tapping screws

Head Fixing (minimum):

  • Single door - none required
  • Paired door - 1 set

Wedging gap:

  • 0 - 15mm

Fire rating for unlined Speedpanel / Korok walls:

  • 51 mm wall: Max. FRR -/60/30
  • 64 mm wall: Max. FRR -/90/30
  • 78 mm wall: Max. FRR -/120/30

Integrity rating can be increased by 30 minutes by lining the wall one or both sides, up to a max. of 120 minutes.

Frame has to be filled with plasterboard, ceramic fibre blanket or grout to achieve 30 minute insulation rating.

F-D-VP30_VP120-S-K5 image
WALL TYPE: Korok / Speedwall
FRAME TYPE: Steel, 1-part

Frame materials available:

  • EGZ - 1.6mm
  • Cold rolled galvanized - 1.6mm

Fasteners:

  • Jamb fixing 6 sets (i.e. 12 per jamb)
  • 10g x 75mm self tapping screws

Head Fixing (minimum):

  • Single door - none required
  • Paired door - 1 set

Wedging gap:

  • 0 - 15mm

Fire rating for unlined Speedpanel / Korok walls:

  • 51 mm wall: Max. FRR -/60/30
  • 64 mm wall: Max. FRR -/90/30
  • 78 mm wall: Max. FRR -/120/30

Integrity rating can be increased by 30 minutes by lining the wall one or both sides, up to a max. of 120 minutes.

Frame has to be filled with plasterboard, ceramic fibre blanket or grout to achieve 30 minute insulation rating.

F-D-VP30_VP120-S-K6 image
WALL TYPE: Korok / Speedwall
FRAME TYPE: Steel, 1-part

Frame materials available:

  • EGZ - 1.6mm
  • Cold rolled galvanized - 1.6mm

Fasteners:

  • Jamb fixing 6 sets (i.e. 12 per jamb)
  • 10g x 75mm self tapping screws

Head Fixing (minimum):

  • Single door - none required
  • Paired door - 1 set

Wedging gap:

  • 0 - 15mm

Fire rating for unlined Speedpanel / Korok walls:

  • 51 mm wall: Max. FRR -/60/30
  • 64 mm wall: Max. FRR -/90/30
  • 78 mm wall: Max. FRR -/120/30

Integrity rating can be increased by 30 minutes by lining the wall one or both sides, up to a max. of 120 minutes.

Frame has to be filled with plasterboard, ceramic fibre blanket or grout to achieve 30 minute insulation rating.

F-D-VP30_VP120-S-K7 image
WALL TYPE: Korok / Speedwall
FRAME TYPE: Steel, 1-part

Frame materials available:

  • EGZ - 1.6mm
  • Cold rolled galvanized - 1.6mm

Fasteners:

  • Jamb fixing 6 sets (i.e. 12 per jamb)
  • 10g x 75mm self tapping screws

Head Fixing (minimum):

  • Single door - none required
  • Paired door - 1 set

Wedging gap:

  • 0 - 15mm

Fire rating for unlined Speedpanel / Korok walls:

  • 51 mm wall: Max. FRR -/60/30
  • 64 mm wall: Max. FRR -/90/30
  • 78 mm wall: Max. FRR -/120/30

Integrity rating can be increased by 30 minutes by lining the wall one or both sides, up to a max. of 120 minutes.

Frame has to be filled with plasterboard, ceramic fibre blanket or grout to achieve 30 minute insulation rating.

F-D-VP30_VP120-S-K8 image
WALL TYPE: Korok / Speedwall
FRAME TYPE: Steel, 1-part

Frame materials available:

  • EGZ - 1.6mm
  • Cold rolled galvanized - 1.6mm

Fasteners:

  • Jamb fixing 6 sets (i.e. 12 per jamb)
  • 10g x 75mm self tapping screws

Head Fixing (minimum):

  • Single door - none required
  • Paired door - 1 set

Wedging gap:

  • 0 - 15mm

Fire rating for unlined Speedpanel / Korok walls:

  • 51 mm wall: Max. FRR -/60/30
  • 64 mm wall: Max. FRR -/90/30
  • 78 mm wall: Max. FRR -/120/30

Integrity rating can be increased by 30 minutes by lining the wall one or both sides, up to a max. of 120 minutes.

Frame has to be filled with plasterboard, ceramic fibre blanket or grout to achieve 30 minute insulation rating.

F-D-VP30_VP120-S-K9 image
WALL TYPE: Korok / Speedwall
FRAME TYPE: Steel, 1-part

Frame materials available:

  • EGZ - 1.6mm
  • Cold rolled galvanized - 1.6mm

Fasteners:

  • Jamb fixing 6 sets (i.e. 12 per jamb)
  • 10g x 75mm self tapping screws

Head Fixing (minimum):

  • Single door - none required
  • Paired door - 1 set

Wedging gap:

  • 0 - 15mm

Fire rating for unlined Speedpanel / Korok walls:

  • 51 mm wall: Max. FRR -/60/30
  • 64 mm wall: Max. FRR -/90/30
  • 78 mm wall: Max. FRR -/120/30

Integrity rating can be increased by 30 minutes by lining the wall one or both sides, up to a max. of 120 minutes.

Frame has to be filled with plasterboard, ceramic fibre blanket or grout to achieve 30 minute insulation rating.

F-D-VP30_VP120-S-K10 image
WALL TYPE: Korok / Speedwall
FRAME TYPE: Steel, 1-part

Note: This installation method is only applicable to 78 mm Korok walls

 

Frame materials available:

  • EGZ - 1.6mm
  • Cold rolled galvanized - 1.6mm

Fasteners:

  • Jamb fixing 6 sets (i.e. 12 per jamb)
  • 10 x 75mm Gauge self tapping screws

Head Fixing (minimum):

  • Single door - none required
  • Paired door - 1 set

Wedging gap:

  • 0 - 15mm

Fire rating for unlined Speedpanel / Korok walls:

  • 78 mm wall: Max. FRR -/120/30

Frame has to be filled with plasterboard, ceramic fibre blanket or grout to achieve 30 minute insulation rating.

F-D-VP30_VP120-S-K11 image
WALL TYPE: Timber stud
FRAME TYPE: Timber

Frame materials available:

  • Hardwood of minimum density 580 kg/m3 (minimum thickness is 30mm)

Fasteners:

  • Frame - Either nailed (75 x 3.2mm) or screwed (10g x 75mm) at 600mm centres. Two fixings per location.
  • Stops - nailed (50 x 3.2mm) at 200mm centres.
  • Architrave - nailed (50 x 3.2mm) at 400mm centres.

Head Fixing (minimum):

  • Single door - none required
  • Paired door - double central fastener required

Stud size:

  • Ex 75 x 50 minimum.

Wedging gap:

  • 0-15mm
F-D-VP30-T-T-3 image
WALL TYPE: Timber stud
FRAME TYPE: Timber

Frame materials available:

  • Hardwood of minimum density 580 kg/m3 (minimum thickness is 42mm)

Fasteners:

  • Frame - Either nailed (75 x 3.2mm) or screwed (10g x 75mm) at 600mm centres nominal. Two fixings per location.
  • Stops - nailed (50 x 3.2mm) at 200mm centres.
  • Architrave - nailed (50 x 3.2mm) at 400mm centres.
  • Pryda Jamb-fixa brackets Type JFB100 at 500mm centres may be used to fix profiles A & B to approved walls.

Stud size:

  • Ex 75x50 minimum.

Wedging gap:

  • 0-10mm
F-D-VP30-T-T-4 image
WALL TYPE: Timber stud
FRAME TYPE: Timber

Frame materials available:

  • Hardwood of minimum density 580 kg/m3 (minimum thickness is 30mm)

Fasteners:

  • Frame - Either nailed (75 x 3.2mm) or screwed (10g x 75mm) at 600mm centres. Two fixings per location.
  • Stops - nailed (50 x 3.2mm) at 200mm centres.
  • Architrave - nailed (50 x 3.2mm) at 400mm centres.

Head Fixing (minimum):

  • Single door - none required
  • Paired door - double central fastener required

Stud size:

  • Ex 75 x 50 minimum.

Wedging gap:

  • 0-15mm
F-D-VP30-T-T-Negative image
WALL TYPE: Timber stud
FRAME TYPE: Steel, 1-part

Frame materials available:

  • EGZ - 1.6mm
  • Cold rolled galvanized - 1.6mm
  • Stainless Steel - 1.5mm

Fasteners:

  • Folded steel connection plates (as shown) to be supplied with frames.
  • Hook onto frame bracing straps and nail or screw to timber studs.
  • Frame connection plates either clouts (30 x 2.5mm gib clouts) or screw fixed.

Head Fixing (minimum):

  • Single door - none required
  • Paired door - single central fastener required

Stud size:

  • Ex 100 x 50 minimum

Wedging gap:

  • Not applicable

Insulation rating:

To obtain an insulation rating, the steel frame must be packed with either;

  • Plasterboard (30 minutes)
  • Ceramic fibre blanket (30 minutes)
  • Cornice plaster (30 minutes)
  • Grout (60 minutes)
  • Pyropanel M4 mortar (60 minutes)

No frame packing equals no insulation rating (i.e. -/xx/-)

F-D-VP30_VP60-S-T-1 image
WALL TYPE: Timber stud
FRAME TYPE: Steel, 1-part

Frame materials available:

  • EGZ - 1.6mm
  • Cold rolled galvanized - 1.6mm
  • Stainless Steel - 1.5mm

Fasteners:

  • Framing stud No.1 screwed to jamb.
  • Connection to stud No.2 via rebated nail on plates. One fastener per location except at bottom where two fasteners are required.
  • Frame to be screw fixed (10g self tapping) at 600mm nominal centres. Two fasteners per location where applicable.

Head Fixing (minimum):

  • Single door - none required
  • Paired door - double central fastener required

Stud size:

  • Ex 100x50 minimum

Wedging gap:

  • Not applicable

Insulation rating:

To obtain an insulation rating, the steel frame must be packed with either;

  • Plasterboard (30 minutes)
  • Ceramic fibre blanket (30 minutes)
  • Cornice plaster (30 minutes)
  • Grout (60 minutes)
  • Pyropanel M4 mortar (60 minutes)

No frame packing equals no insulation rating (i.e. -/xx/-)

F-D-VP30_VP60-S-T-2 image
WALL TYPE: Timber stud
FRAME TYPE: Steel, 1-part

Frame materials available:

  • EGZ - 1.6mm
  • Cold rolled galvanized - 1.6mm
  • Stainless Steel - 1.5mm

Fasteners:

  • Frame screwed to stud through Gib Fyreline packing between stud and shims.
  • Frame to be screw fixed (10g self tapping) at 600mm nominal centres. Two fasteners per location where applicable.

Head Fixing (minimum):

  • Single door - none required
  • Paired door - double central fastener required

Stud size:

  • Ex 100 x 50 minimum

Wedging gap:

  • 0-10mm

Insulation rating:

To obtain an insulation rating, the steel frame must be packed with either;

  • Plasterboard (30 minutes)
  • Ceramic fibre blanket (30 minutes)
  • Cornice plaster (30 minutes)
  • Grout (60 minutes)
  • Pyropanel M4 mortar (60 minutes)

No frame packing equals no insulation rating (i.e. -/xx/-)

F-D-VP30_VP60-S-T-3 image
WALL TYPE: Timber stud
FRAME TYPE: Steel, 1-part

Frame materials available:

  • EGZ - 1.6mm
  • Cold rolled galvanized - 1.6mm
  • Stainless Steel - 1.5mm

Fasteners:

  • Frames may be screwed directly to studs either through the stud and into the frame bracing straps or through the frame into the timber stud at 600mm centres nominal.
  • Frame to be screw fixed (10g self tapping) at 600mm centres nominal. Two fasteners per location where applicable.

Head Fixing (minimum):

  • Single door - none required
  • Paired door - double central fastener required

Stud size:

  • Ex 100 x 50 minimum

Wedging gap:

  • Not applicable

Insulation rating:

To obtain an insulation rating, the steel frame must be packed with either;

  • Plasterboard (30 minutes)
  • Ceramic fibre blanket (30 minutes)
  • Cornice plaster (30 minutes)
  • Grout (60 minutes)
  • Pyropanel M4 mortar (60 minutes)

No frame packing equals no insulation rating (i.e. -/xx/-)

F-D-VP30_VP60-S-T-4 image
WALL TYPE: Timber stud
FRAME TYPE: Steel, 1-part

Frame materials available:

  • Cold rolled galvanized - 1.6mm packed with pla board

Fasteners:

  • Frame to be screw fixed with 10-14 x 75mm gauge counter sunk screws at 600mm centres nominal.

Head Fixing (minimum):

  • Single door - non required
  • Paired door - double central fastener required

Stud Size

  • Ex 100 x 50 minimum

Wedging gap:

  • 0 - 10mm

Insulation rating:

To obtain an insulation rating, the steel frame must be packed with either;

  • Plasterboard (30 minutes)
  • Ceramic fibre blanket (30 minutes)
  • Cornice plaster (30 minutes)
  • Grout (60 minutes)
  • Pyropanel M4 mortar (60 minutes)

No frame packing equals no insulation rating (i.e. -/xx/-)

F-D-VP30_VP60-S-Hardie_1 image
WALL TYPE: Timber stud
FRAME TYPE: Steel, 1-part

Frame materials available:

  • Cold rolled galvanized - 1.6mm packed with pla board

Fasteners:

  • Frame to be screw fixed with 10 x 75mm gauge screws at 600mm centres nominal.

Head Fixing (minimum):

  • Single door - non required
  • Paired door - double central fastener required

Stud Size

  • Ex 100 x 50 minimum

Wedging gap:

0 - 10mm

Insulation rating:

To obtain an insulation rating, the steel frame must be packed with either;

  • Plasterboard (30 minutes)
  • Ceramic fibre blanket (30 minutes)
  • Cornice plaster (30 minutes)
  • Grout (60 minutes)
  • Pyropanel M4 mortar (60 minutes)

No frame packing equals no insulation rating (i.e. -/xx/-)

F-D-VP30_VP60-S-Hardie_2 image
WALL TYPE: Timber stud
FRAME TYPE: Steel, 1-part

Gib Universal wall systems - One way FRR only

Please refer to Gib Fire Rated Systems manual for thickness and number of lining boards.

Frame materials available:

  • EGZ - 1.6mm
  • Cold rolled galvanized - 1.6mm

Fasteners:

  • Framing stud No.1 screwed to jamb.
  • Connection to stud No.2 via rebated nail on plates. One fastener per location except at bottom where two fasteners are required.
  • Frame to be screw fixed (10g self tapping) at 600mm nominal centres. Two fasteners per location where applicable.

Head Fixing (minimum):

  • Single door - none required
  • Pair door - single central fastener required

Stud size:

  • Ex 100 x 50 minimum

Wedging gap:

  • Not applicable

Insulation rating:

To obtain an insulation rating, the steel frame must be packed with either;

  • Plasterboard (30 minutes)
  • Ceramic fibre blanket (30 minutes)
  • Cornice plaster (30 minutes)
  • Grout (60 minutes)
  • Pyropanel M4 mortar (60 minutes)

No frame packing equals no insulation rating (i.e. -/xx/-)

F-D-VP30_VP90-S-Uni image
WALL TYPE: Timber stud
FRAME TYPE: Steel, 1-part

Gib Universal wall systems - One way FRR only

Please refer to Gib Fire Rated Systems manual for thickness and number of lining boards.

Frame materials available:

  • Cold rolled galvanized - 1.6mm

Fasteners:

  • Frame screwed to stud
  • Frame to be screw fixed (10g self tapping) at 600 mm nominal centres. Two fasteners per location where applicable

Head Fixing (minimum):

  • Single door - none required
  • Pair door - double central fastener required

Stud size:

  • Ex 100 x 50 minimum

Wedging gap:

  • 0-10 mm

Insulation rating:

To obtain an insulation rating, the steel frame must be packed with either;

  • Plasterboard (30 minutes)
  • Ceramic fibre blanket (30 minutes)
  • Cornice plaster (30 minutes)
  • Grout (60 minutes)
  • Pyropanel M4 mortar (60 minutes)

No frame packing equals no insulation rating (i.e. -/xx/-)

F-D-VP30_VP90-S-Uni2 image
WALL TYPE: Timber stud
FRAME TYPE: Steel, 1-part

Frame materials available:

  • EGZ - 1.6mm
  • Cold rolled galvanized - 1.6mm

Fasteners:

  • Frame screwed to stud through Gib Fyreline packing between stud and shims.
  • Frame to be screw fixed (10g self tapping) at 600mm nominal centres. Two fasteners per location where applicable.

Head Fixing (minimum):

  • Single door - none required
  • Paired door - single central fastener required

Stud size:

  • Ex 100 x 50 minimum

Wedging gap:

  • 0-10mm

Insulation rating:

To obtain an insulation rating, the steel frame must be packed with either;

  • Plasterboard (30 minutes)
  • Ceramic fibre blanket (30 minutes)
  • Cornice plaster (30 minutes)
  • Grout (60 minutes)
  • Pyropanel M4 mortar (60 minutes)

No frame packing equals no insulation rating (i.e. -/xx/-)

F-D-VP30_120-S-T-R image
WALL TYPE: Timber stud
FRAME TYPE: Steel, 1-part

Frame materials available:

  • EGZ - 1.6mm
  • Cold rolled galvanized - 1.6mm

Fasteners:

  • Frame screwed to stud through frame wings
  • Frame to be screw fixed (10g self tapping) at 600mm nominal centres

Head Fixing (minimum):

  • Single door - none required
  • Paired door - single central fastener required

Stud size:

  • Ex. 100x50 mm minimum

Wedging gap:

  • 0-10mm

Insulation rating:

To obtain an insulation rating, the steel frame must be packed with either;

  • Plasterboard (30 minutes)
  • Ceramic fibre blanket (30 minutes)
  • Cornice plaster (30 minutes)
  • Grout (60 minutes)
  • Pyropanel M4 mortar (60 minutes)

No frame packing equals no insulation rating (i.e. -/xx/-)

F-D-VP30_VP60-S-T-Negative image
WALL TYPE: Timber stud
FRAME TYPE: Steel, 1-part

Gib GWTLE30 wall specification

 

Frame materials available:

  • Cold rolled galvanized - 1.6mm packed with plaster board

Fasteners:

  • Frame to be screw fixed with 10-14 x 75mm gauge counter sunk screws at 600mm centres nominal.

Head Fixing (minimum):

  • Single door - non required
  • Paired door - double central fastener required

Stud Size

  • Ex 100 x 50 minimum

Wedging gap:

  • 0 - 10mm

Insulation rating:

To obtain an insulation rating, the steel frame must be packed with either;

  • Plasterboard (30 minutes)
  • Ceramic fibre blanket (30 minutes)
  • Cornice plaster (30 minutes)
  • Grout (30 minutes)
  • Pyropanel M4 mortar (30 minutes)

No frame packing equals no insulation rating (i.e. -/xx/-)

F-D-VP30-S-GWTLE30 image
WALL TYPE: Timber stud
FRAME TYPE: Steel, 2-part
F-D-VP30_ 60 2 Part-S-T-2 image
WALL TYPE: Timber stud
FRAME TYPE: Steel, 2-part

Frame materials available:

  • EGZ - 1.6mm
  • Cold rolled galvanized - 1.6mm

Fasteners:

  • Frame to be screw fixed (10g self tapping) at 600mm nominal centres through frame straps and timber packers into timber stud.
  • Standard is 4 no. per jamb (front section) and 2 no. per jamb (rear section)

Head Fixing (minimum):

  • Single door - none required
  • Paired door - 2 no. fasteners required (front section only)

Stud size:

  • Ex 100 x 50 minimum

Wedging gap:

  • 0-10mm

Insulation rating:

To obtain an insulation rating, all voids in the steel frame and wedging gaps must be packed with either;

  • Plasterboard (30 minutes)
  • Ceramic fibre blanket, 96 kg/m3 min. (30 minutes)
  • Mineral wool blanket, 96 kg/m3 min. (30 minutes)

No frame packing equals no insulation rating (i.e. -/xx/-)

F-D-VP30_60 2 Part-S-T-1 image
WALL TYPE: Masonry
FRAME TYPE: Timber

Frame materials available:

  • Hardwood of minimum density 580 kg/m3 (minimum thickness is 30mm)

Fasteners:

  • Frame - M8 or M10 'Ramset' Dynabolts at 600mm centres nominal. Fixings on or near centre of frame jamb.
  • Stops - nailed (50 x 3.2mm) at 200mm centres.
  • Architrave -nailed (50 x 3.2mm) at 400mm centres.

Head Fixing (minimum):

  • Single door - none required
  • Paired door - single central fastener required

Wedging gap:

  • 0-15mm
F-D-VP30-T-M image
WALL TYPE: Masonry
FRAME TYPE: Steel, 1-part

Frame materials available:

  • EGZ - 1.6mm
  • Cold rolled galvanized - 1.6mm
  • Stainless Steel - 1.5mm (Must be fully grouted frame VP90-120)

Fasteners:

  • Jamb fixing at 600mm centres minimum
  • Expansion anchors eg. M10 countersunk 'Ramset' Dynabolts
  • M12 countersunk masonry screwbolts

Head Fixing (minimum):

  • Single door - none required
  • Paired door - single central fastener required

Wedging Gap:

  • 0-15mm

Insulation rating:

To obtain an insulation rating, the steel frame must be packed with either;

  • Plasterboard (30 minutes)
  • Ceramic fibre blanket (30 minutes)
  • Cornice plaster (30 minutes)
  • Grout (60 minutes)
  • Pyropanel M4 mortar (60 minutes)

No frame packing equals no insulation rating (i.e. -/xx/-)

F-D-VP30_VP120-S-M image
WALL TYPE: Masonry
FRAME TYPE: Steel, 2-part

Frame materials available:

  • EGZ - 1.6mm
  • Cold rolled galvanized - 1.6mm
  • Stainless Steel - 1.5mm

Fasteners:

  • Frame to be fixed with masonry anchors or screw bolts. Standard is 4 No. per Jamb. Rear insert fixed to frame with machine screws (drilled and tapped on site).

Head Fixing (minimum):

  • Single door - none required
  • Paired door - 2 No. fasteners required (Front section only)

Wedging gap:

  • Not applicable

Insulation rating:


To obtain an insulation rating, the steel frame must be packed with either;

  • Plasterboard (30 minutes)
  • Ceramic wool, 96 kg/m3 (30 minutes)

No frame packing equals no insulation rating (i.e. -/xx/-)

 

F-D-VP30_60 2 part-S-M image
WALL TYPE: Steel stud
FRAME TYPE: Timber

Frame materials available:

  • Hardwood of minimum density 580 kg/m3 (minimum thickness is 30mm)

Fasteners:

  • Frame - Screwed (10g self tapping) at 600mm centres nominal. Minimum of one screw per location. Frames may also be installed by screw fixing the steel studs to the back of the timber frame during wall construction.
  • Stops - nailed (50 x 3.2mm) at 200mm centres.
  • Architrave - nailed (50 x 3.2mm) at 400mm centres.

Head Fixing (minimum):

  • Single door - none required
  • Paired door - double central fastener required

Stud size:

  • 65 x 34mm minimum of 0.55 MSG gauge.

Wedging gap:

  • 0-10mm
F-D-VP30-T-S-3 image
WALL TYPE: Steel stud
FRAME TYPE: Steel, 1-part

Frame materials available:

  • EGZ - 1.6mm
  • Cold rolled galvanized - 1.6mm
  • Stainless Steel - 1.5mm

Fasteners:

  • Frame screwed to boxed stud at 600mm centres nominal with self tapping screws.
  • Steel studs may be riveted (steel pop rivets) or screwed (10g self tapping) to the frame bracing straps at 600mm centres nominal.

Head Fixing (minimum):

  • Single door - none required
  • Paired door - double central fastener required

Stud size:

  • 65 x 34mm minimum of 0.55 SMG gauge

Wedging gap:

  • Not applicable

Insulation rating:

To obtain an insulation rating, the steel frame must be packed with either;

  • Plasterboard (30 minutes)
  • Ceramic fibre blanket (30 minutes)
  • Cornice plaster (30 minutes)
  • Grout (60 minutes)
  • Pyropanel M4 mortar (60 minutes)

No frame packing equals no insulation rating (i.e. -/xx/-)

F-D-VP30_VP60-S-S-2 image
WALL TYPE: Steel stud
FRAME TYPE: Steel, 1-part

Frame materials available:

  • EGZ - 1.6mm
  • Cold rolled galvanized - 1.6mm
  • Stainless Steel - 1.5mm

Fasteners:

  • Frame screwed to boxed studs with packing steel shims at 600mm centres nominal.
  • Steel studs may be riveted (steel pop rivets) or screwed (10g self tapping) to the frame bracing straps at 600mm centres nominal.

Head Fixing (minimum):

  • Single door - none required
  • Paired door - double central fastener required

Stud size:

  • 92 x 34mm minimum of 0.55 SMG gauge

Wedging Gap:

  • 0-10mm

Insulation rating:

To obtain an insulation rating, the steel frame must be packed with either;

  • Plasterboard (30 minutes)
  • Ceramic fibre blanket (30 minutes)
  • Cornice plaster (30 minutes)
  • Grout (60 minutes)
  • Pyropanel M4 mortar (60 minutes)

No frame packing equals no insulation rating (i.e. -/xx/-)

F-D-VP30_VP60-S-S-3 image
WALL TYPE: Steel stud
FRAME TYPE: Steel, 1-part

Frame materials available:

  • EGZ - 1.6mm
  • Cold rolled galvanized - 1.6mm

Fasteners:

  • Frame screwed to stud through Gib Fyreline packing between stud and shims.
  • Frame to be screw fixed (10g x 50mm self tapping) at 600mm nominal centres. Two fasteners per location where applicable.

Head Fixing (minimum):

  • Single door - none required
  • Paired door - single central fastener required

Stud size:

  • 92 x 34mm minimum of 0.55 SMG gauge

Wedging gap:

  • 0-10mm

Insulation rating:

To obtain an insulation rating, the steel frame must be packed with either;

  • Plasterboard (30 minutes)
  • Ceramic fibre blanket (30 minutes)
  • Cornice plaster (30 minutes)
  • Grout (60 minutes)
  • Pyropanel M4 mortar (60 minutes)

No frame packing equals no insulation rating (i.e. -/xx/-)

F-D-VP30_120-S-S-R image
WALL TYPE: Steel stud
FRAME TYPE: Steel, 1-part

Frame materials available:

  • EGZ - 1.6mm
  • Cold rolled galvanized - 1.6mm

Fasteners:

  • Frame screwed to stud through frame wings
  • Frame to be screw fixed (10g self tapping) at 600mm nominal centres

Head Fixing (minimum):

  • Single door - none required
  • Paired door - single central fastener required

Stud size:

  • 65 x 34mm minimum of 0.55 MSG gauge.

Wedging gap:

  • 0-10mm

Insulation rating:

To obtain an insulation rating, the steel frame must be packed with either;

  • Plasterboard (30 minutes)
  • Ceramic fibre blanket (30 minutes)
  • Cornice plaster (30 minutes)
  • Grout (60 minutes)
  • Pyropanel M4 mortar (60 minutes)

No frame packing equals no insulation rating (i.e. -/xx/-)

F-D-VP30_60-S-S-Negative image
WALL TYPE: Steel stud
FRAME TYPE: Steel, 2-part

Frame materials available:

  • EGZ - 1.6mm
  • Cold rolled galvanized - 1.6mm

Fasteners:

  • Frame to be screw fixed (10g self tapping) at 600mm nominal centres through frame straps and GiB Fyreline into timber stud.
  • Standard is 4 no. per jamb (front section) and 2 no. per jamb (rear section)

Head Fixing (minimum):

  • Single door - none required
  • Paired door - 2 no. fasteners required (front section only)

Stud size:

  • 65 x 34mm minimum of 0.55 SMG gauge

Wedging gap:

  • 0-10mm

Insulation rating:

To obtain an insulation rating, all voids in the steel frame and wedging gaps must be packed with either;

  • Plasterboard (30 minutes)
  • Ceramic fibre blanket, 96 kg/m3 min. (30 minutes)
  • Mineral wool blanket, 96 kg/m3 min. (30 minutes)

No frame packing equals no insulation rating (i.e. -/xx/-)

F-D-VP30_60 2 Part-S-S-1 image